PMF Analysis (Probable Maximum Flood) in South Africa

PMF hydrology for high-consequence dams and structures: storm maximisation, catchment and reservoir routing, and sensitivity tests in line with SANCOLD guidelines.

Talk to an engineer

What we typically need from you

  • Dam classification, consequence category, and applicable guideline references
  • Catchment characteristics, reservoir rule curves, and spillway geometry datasets
  • Prior PMF studies or independent review comments to address
  • Meteorological product preferences or transposition constraints from the safety panel

Where we add technical depth

  • Storm maximisation and duration logic documented for critical duration selection
  • Catchment routing consistent with reservoir storage, spillway performance, and gates
  • Sensitivity matrix for contested assumptions (losses, transposition)
  • Appendix structure suited to dam safety reviewers and legal disclosure if required

When do you need this?

  • High-consequence dams where extreme flood estimates govern safety
  • Regulatory or insurer requests for PMF demonstration
  • Comparing PMF vs PMP/PMF scenarios for sensitivity

Our approach

  1. Standard selection

    Agree the hydrometeorological standard and documentation expectations for the safety case.

  2. Storm maximisation

    Construct critical duration storms and transposition logic where applicable.

  3. Catchment routing

    Route losses and hydrographs consistently with reservoir and spillway modelling.

  4. Reporting

    Deliver a memorandum with appendices and sensitivity tests, set out so a reviewer can re-derive the critical duration and inflow.

What you'll receive

  • PMF hydrology memorandum
  • Hydrographs and key tables
  • Sensitivity documentation

Relevant SA standards

  • SANCOLD guidelines for extreme floods
  • DWS dam safety regulatory context

FAQ

How does the PMF differ from the design flood?

The design flood (SANCOLD's Recommended Design Discharge) is a return-period flood the spillway must pass without damage. The PMF is an extreme flood the dam must survive without failing; the dam's size class and hazard rating set whether the full PMF or a fraction applies.

Do you include climate change?

Where the brief requires it, we agree the sensitivity approach with you and document it alongside the other contested assumptions, such as losses and transposition.

Do you support independent review?

Yes. The appendices are structured for dam safety reviewers, with transposition, losses and routing decisions set out so another specialist can re-derive the critical duration and inflow. We respond to technical queries and address prior independent review comments you send us.

How do you handle storm transposition?

Where transposition applies, we construct critical duration storms and document the transposition logic, including any constraints set by the safety panel. Transposition is one of the contested assumptions tested in the sensitivity matrix.

How is reservoir routing handled?

Catchment hydrographs are routed consistently with reservoir storage, spillway performance and gates, using your rule curves and spillway geometry. We address routing stability, spillway split flows and sensitivity to initial reservoir level up front.

Author

Robert Fortuin

Areas we serve

We work on projects across South Africa — see locations.

Ready to get started?

Contact us

Doing it yourself? Our engineering platform at studio.deltahydro.tech supports workflows in this service area.