What Is a Floodline Certificate, and When Does a Municipality Ask for One?
· Written by Robert Fortuin · Reviewed by Stephan Dreyer
A floodline certificate is an engineer’s signed statement that the floodlines drawn on a plan were determined for the stated flood, usually the 1:100-year flood and often the 1:50-year flood as well. Every township layout needs the 1:100-year floodline under section 144 of the National Water Act, and municipalities extend the requirement to other applications through their land use schemes and planning forms. Who may sign, and how old the line may be, depends on the municipality.
Need a certified floodline for an application? We determine the 1:50 and 1:100-year lines, and our reports are signed by a registered professional engineer.
Floodline determinationWhere the requirement comes from
Section 144 of the National Water Act says that “no person may establish a township unless the layout plan shows, in a form acceptable to the local authority concerned, lines indicating the maximum level likely to be reached by floodwaters on average once in every 100 years.” It applies to township establishment everywhere in the country. It does not say who must determine the line or sign for it; the phrase “in a form acceptable to the local authority” leaves that to the municipality.
Municipalities then reach further, through their land use schemes, planning by-laws and application forms. Our guide to every law that applies to a site near a river shows how the floodline fits with the other approvals.
Which applications need one
| Municipality | When a certified floodline is required | Source |
|---|---|---|
| Every municipality | Township establishment: the 1:100-year floodline on the layout plan | National Water Act, s144 |
| Tshwane | Any application the City specifies: the 1:50 and 1:100-year floodlines on the diagram or layout plan, certified by a professional engineer | Land Use Scheme 2024, cl 18(10)(h) |
| Ekurhuleni | Township establishment and, where applicable, rezoning | Spatial planning by-law application forms |
| Polokwane | Building on land likely to flood once in 100 years needs approval, with the floodline on the plans and an engineer’s certificate; township layouts need the 1:50 and 1:100-year lines certified and not more than three years old | Integrated Land Use Scheme 2022, cl 13; Planning By-law, form F-10(A1) |
| Mbombela | Township layout plans; the 2025/26 user guide adds subdivision, consolidation and farm rezoning, “if applicable” | Spatial Planning and Land Use Management By-law; user guide 2025/26 |
| Msunduzi (Pietermaritzburg) | The 1:50 and 1:100-year lines, determined by a registered professional engineer, where the Municipality asks for them | Single Land Use Scheme 2024, cl 5.43 |
| Nelson Mandela Bay | Land use applications list a “flood line determination and/or report” as a supporting document | Land use application form |
| Cape Town | Development in the floodplain needs a report by a suitably qualified registered engineering professional; where floodlines have not been determined, the developer appoints one before detailed planning | Floodplain and River Corridor Management Policy 2009 |
Smaller municipalities that publish no rule, such as Knysna and Sol Plaatje, set requirements case by case. Our city pages cover the local rules in more detail.
Who may sign
There is no national rule. Where a municipality names anyone, it names an engineer:
- Johannesburg: the stormwater by-laws define the floodplain as determined by a professional engineer, meaning a registered professional engineer or technologist approved by the Johannesburg Roads Agency.
- Tshwane, Polokwane and Msunduzi: a registered professional engineer.
- Cape Town: a “suitably qualified registered engineering professional” determines the floodlines and reports on development in the floodplain.
We found no municipality that names a SACNASP-registered scientist for floodlines. SACNASP registration matters for a different document: the risk matrix for a water use authorisation in the regulated area of a watercourse. Our post on who determines a floodline covers what to ask before you appoint anyone.
How old a floodline can be
Polokwane is the only municipality we found with a fixed limit: three years, for township establishment. Elsewhere, a reviewer can still reject a line that no longer reflects the site, for example after new development upstream, a new bridge or a major flood. Our post on why floodlines go out of date lists the causes.
What the certificate should state
Forms differ, but a certificate a reviewer can rely on usually sets out:
- the watercourse and the reach the lines cover;
- the return periods shown (1:100-year, and 1:50-year where asked for);
- the survey or terrain data the model used, and its date;
- whether the lines are drawn to the water surface or the energy level (Cape Town uses the energy level);
- the report that explains the method, and its date;
- the engineer’s name, registration number and signature.
A certificate without the report behind it is weak evidence. Reviewers check the design flood, the model and the assumptions, so the report is what gets the line accepted. Our post on what reviewers check in a floodline study covers that side.
See our floodline determination service, or send us the site and the application type and we will tell you what the municipality is likely to ask for.
This post explains the documents listed below. It is not legal advice; requirements change and are applied case by case, so confirm them with the relevant authority before relying on them.
Documents referenced
Links go to official government copies wherever one is published online. Check for amendments before relying on a specific clause.
- National Water ActAct · Act 36 of 1998 · Department of Water and Sanitation
- Tshwane Land Use Scheme 2024 (listing page)By-law · City of Tshwane
- Stormwater Management By-laws, 2010By-law · City of Johannesburg
- Spatial Planning and Land Use Management By-law formsGuideline · City of Ekurhuleni
- Polokwane Integrated Land Use Scheme 2022By-law · Polokwane Municipality
- Municipal Planning By-law (amended 2025)By-law · Polokwane Municipality
- Single Land Use Scheme (October 2024)By-law · Msunduzi Municipality
- Land use application formGuideline · Nelson Mandela Bay Metropolitan Municipality
- Floodplain and River Corridor Management PolicyPolicy · City of Cape Town
- Spatial Planning and Land Use Management By-lawBy-law · City of Mbombela
- User guide: applications in terms of the Spatial Planning and Land Use Management By-law (2025/26)Guideline · City of Mbombela