How to Get Permission to Build Inside a Floodplain in South Africa
· Written by Stephan Dreyer · Reviewed by Robert Fortuin
There is no single permit for building in a floodplain. Depending on the site and the works, you may need approvals from three different authorities: the municipality (land use, stormwater and building plans), the Department of Water and Sanitation (a water use authorisation) and the provincial environment department (environmental authorisation). Each asks for overlapping evidence, and each runs on its own clock. The first question is whether the municipality allows the development at all.
Planning to build in or next to a floodplain? We prepare the floodline and flood assessment every one of these approvals relies on, and the water use application.
Floodline determinationStep 1: Map the lines
Every approval depends on where the site sits relative to:
- the 1:50 and 1:100-year floodlines;
- the riparian edge and any wetlands, which with the floodline define the regulated area of the watercourse;
- 32 m from the edge of the watercourse, which can trigger environmental authorisation;
- the municipality’s own buffers.
Our post on the lines that control building near a river explains each one. Without a floodline, nothing else can be scoped.
Step 2: Check whether the municipality allows it
Some municipalities bar development in parts of the floodplain outright:
| Municipality | Rule | Source |
|---|---|---|
| Cape Town | No new rights, and no exercising of existing rights, in the high hazard zone; formal residential development not permitted below the 1:50-year line; filling not permitted below the 1:50-year line | Floodplain and River Corridor Management Policy 2009 |
| Johannesburg | No development within the area flooded by a 1:100-year flood, or within the riparian zone plus a buffer of 30, 32 or 50 m, whichever is greater | Land Use Scheme 2018 (2025 review), cl 50(3)(a) |
| Msunduzi (Pietermaritzburg) | No habitable buildings within the 1:50-year floodline | Single Land Use Scheme 2024, cl 5.43 |
| Nelson Mandela Bay | The Municipality may prohibit buildings, or set conditions, within the 50- to 100-year floodline | Land Use Scheme 2023, cl 56 |
| George | May refuse new permanent residential, commercial or industrial development under the 50-year floodline | Stormwater By-law 2023, s26(4)(c) |
| Polokwane | No building on land likely to flood once in 100 years without approval; floodline certified by a registered professional engineer | Integrated Land Use Scheme 2022, cl 13 |
| Mbombela | No building below the 1:100-year line unless the City approves the construction method | Land Use Scheme 2019, cl 5.17.2(d) |
Where the scheme allows development on conditions, the conditions usually cover floor levels, an engineer’s certificate that flood levels elsewhere will not rise, and sometimes a restriction registered against the title.
Step 3: The approvals, and how long each takes
| Approval | Authority | When you need it | Statutory timeframe |
|---|---|---|---|
| Land use application (rezoning, subdivision, consent use, departure) | Municipality | Where the development needs new or changed rights; many municipalities require a floodline certificate with it | Set by each municipality’s planning by-law |
| Stormwater consent or permit | Municipality | Cape Town and eThekwini: any activity that may raise flood levels; Johannesburg: major developments, clearing in a floodplain, berms | Case by case |
| Water use registration under the General Authorisation | Department of Water and Sanitation | Work in the regulated area of a watercourse rated Low risk on the risk matrix. A single residential house (with any French drain or conservancy tank at least 100 m from a watercourse) needs registration but no risk matrix | Confirmation within 30 working days of the Department accepting that the submission meets all the notice’s requirements (GN 4167, cl 7(7)(b)) |
| Water use licence | Department of Water and Sanitation | Medium or High risk work, or work the General Authorisation excludes (such as anything that stores water) | Up to 300 days under the 2017 regulations, excluding 15 December to 5 January. The Department said in 2021 that complete applications lodged from April 2021 would be finalised within 90 days |
| Environmental authorisation (basic assessment) | Usually the provincial environment department; sometimes the national department | Listed activities such as structures of 100 m² or more within 32 m of a watercourse (outside urban areas and existing road reserves), or moving more than 10 m³ in one | Report due within 90 days of the application, or 140 days if a second round of public participation is needed; decision within 107 days of receiving the report; at least 30 days of public participation |
| Building plans | Municipality | Every building, other than minor building work the municipality exempts | 30 days for buildings under 500 m², 60 days for 500 m² or larger (Building Standards Act, s7(1)) |
These run partly in parallel, but the water use and environmental approvals usually take longest, and a municipality may ask to see them before it approves building plans. Our guide to every law that applies to a site near a river sets out what triggers each.
What every application needs
The same engineering evidence supports all of them:
- The floodline, pre- and post-development. See pre- vs post-development floodlines.
- The effect on others: a difference map showing the change in flood level and velocity at neighbouring boundaries. See will my development flood my neighbours?
- Floor and platform levels with the freeboard the municipality requires. See freeboard.
- Compensatory storage where fill is placed in the floodplain. See filling in a floodplain.
- The DWS risk matrix, completed by a SACNASP-registered professional, for work in the regulated area.
- A stormwater management plan where the municipality requires attenuation.
The order that saves time
- Commission the floodline and the riparian delineation.
- Confirm with the municipality what it will allow, before the layout is fixed.
- Design the layout around the lines, keeping buildings and fill out of the hazard zones where possible.
- Lodge the water use and environmental applications early; they take longest.
- Submit the land use application and building plans with the engineering evidence attached.
See our floodline determination and water use licence services, or send us the site details and we will tell you which approvals apply.
This post explains the documents listed below. It is not legal advice; requirements change and are applied case by case, so confirm them with the relevant authority before relying on them.
Documents referenced
Links go to official government copies wherever one is published online. Check for amendments before relying on a specific clause.
- National Water ActAct · Act 36 of 1998 · Department of Water and Sanitation
- General Authorisation for water uses under section 21(c) and (i)Regulations · GN 4167 of 2023 · Department of Water and Sanitation
- Regulations regarding the procedural requirements for water use licence applications and appealsRegulations · GN R267 of 2017 · Department of Water and Sanitation
- EIA Regulations 2014 (as amended in 2017)Regulations · GN R982 of 2014, amended by GN 326 of 2017 · Department of Environmental Affairs (gazette copy on FAOLEX)
- National Building Regulations and Building Standards ActAct · Act 103 of 1977 · Parliament of South Africa
- Floodplain and River Corridor Management PolicyPolicy · City of Cape Town
- City of Johannesburg Land Use Scheme 2018 (2025 review)By-law · City of Johannesburg
- Single Land Use Scheme (October 2024)By-law · Msunduzi Municipality
- Nelson Mandela Bay Land Use Scheme 2023 (Provincial Gazette 4981)By-law · Nelson Mandela Bay Metropolitan Municipality
- By-law relating to Stormwater, 2023By-law · George Municipality
- Polokwane Integrated Land Use Scheme 2022By-law · Polokwane Municipality
- City of Mbombela Land Use Scheme 2019By-law · City of Mbombela